Make three columns: contract deadlines, property financing milestones, and cash owed by the operating business. Add deposits, lender and landlord consents where relevant, and the first payroll. Mark the milestones linked under the signed documents and confirm those dependencies with counsel.
If a 30-day delay costs $35,000 and the buyer has $25,000 above the opening operating reserve, at least $10,000 needs a funding source or a negotiated change. Decide who carries that exposure before relying on an extension.