Build a Buyer Forecast With a Delayed Integration Case

By Don McClain | Founder & Principal, Medro Advisors

Start with the seller’s reported baseline and list buyer changes one at a time. If a proposed new supplier would save $5,000 per month but cannot start for 90 days, defer the $15,000 in first-quarter savings and include any overlap cost. Then compare payroll, debt payments and cash reserve against that slower case. Identify what evidence supports the change and who owns the implementation date.